A NEW OLD BARN
The UNA is making plans to have the Old Barn Community Centre renovated! Learn more about the upcoming changes below.
The UNA is making plans to have the Old Barn Community Centre renovated! Learn more about the upcoming changes below.
We are prioritizing the maintenance and upkeep of our beloved Barn’s iconic roof to keep it the shining historical jewel that it is for many years to come.
Renovation starts: Late September 2023 | Duration: Approximately 3-4 weeks
Update: December 14, 2023
The Old Barn Community Centre roof repair is completed. Scaffolding is expected to be removed in the last week of December 2023.
For questions, please contact operations@myuna.ca.
New equipment, a new room layout and new fitness programs are coming your way as we upgrade the Old Barn Fitness Centre to meet your fitness needs.
Renovation starts: September 25, 2023 | Duration: Approximately two weeks
Update: October 13, 2023
Renovation is now complete and the Fitness Centre will be open for use starting Monday October 16, 2023.
Our community is changing and so should our shared spaces! The new Living Room will be redesigned with better space functionality and comfortable furniture.
Renovation starts: September 4, 2023 | Duration: Approximately two weeks
Update: October 13, 2023
Renovation is now complete and the Living Room will be open for use starting Monday October 16, 2023.
Our highly versatile meeting rooms are getting outfitted with a brand new projector and audio-visual hardware to make sure your events run smoothly.
Renovation starts: October 2023 | Duration: Approximately one week
Update: October 20, 2023
Renovation is now complete.
New equipment, a new room layout and new fitness programs are coming your way as we upgrade the Old Barn Fitness Centre to meet your fitness needs. We apologize for the inconvenience as we upgrade our facilities.